We're moving and building
1370 E. Robindale
Las Vegas, NV
89123
You can see the existing house and plenty of space on the large lot where the new worship area will be built.
Here are some important dates for the project. These are estimates and will be updated as needed so work teams can plan each stage.
- May 27 - CLOSED
- May 28 - Planned and put up tent, decided not to use it.
- May 30 - Tore down wall for temporary church location.
- May 31 - Begin Permit process for Civil Engineering Permits.
- June 4 - Last Day in Pecos property, final cleanup. Final preparation at Robindale property for worship.
- June 5 - First Worship service in New facility.
- July
- - Remodeling house into church.
- - Installing irrigation and moving trees and shrubs.
- August Work - Exterior house work, painting, roofing, trimwork.
- September work - Parking lot and site plan work.
- ??? December ??? - Civil engineering work done, permit submission
-
??? January ??? - Groundbreaking on new facility, permits in place
- need lots of volunteer help here!
Click on the camera icon to view photos from each major stage.
Contact Steve Wunderink for setting up and coordinating work teams:
steve@gracevalleychurch.org
(702) 561-5619
-
Our estimated cost for the worship center project is $120,000. BUT, this can be reduced with your volunteer labor and donated material. To the left is the current [as of July 28] status of our budget.
-
Donated money
-
Donated material
-
Donated labor
-
Still needed - $33,000
- Donations can be sent to:
GVCRC
1370 E. Robindale
Las Vegas, NV 89123